Construction Support Services for Del Amo Blvd. Extension, T-30, Phase 2
2010-2012
This project includes construction management of a new 4-lane roadway (Del Amo Blvd) between Crenshaw Blvd and Maple Ave and widen an existing segment between Maple Ave and Prairie Ave. Also includes a new bridge over the BNSF Railway's mainline tracks, MSE retaining walls, drainage improvements, relocation of a railroad spur track, reconstruction of affected off-site facilities and coordination with Southern California Edison and ExxonMobil Oil for relocation of their respective facilities. Construction cost is estimated to total between $13.5M and $15M and will be partially funded by the American Recovery and Reinvestment Act (ARRA).