Transportation Case Studies

transportation services

orange county transportation authority

Project Elements:
  • Risk Analysis
  • Identification of high priority areas of review
  • Plan Review

Third Party Plan Review – 5 Grade Separations BNSF Orangethorpe: The scope of this project is intended to minimize OCTA's risk in the delivery of five grade separations during design and construction. Click here to learn more...

transportation services

orange county transportation authority

Project Elements:
  • Multiple Agency Integration
  • Project Coordination

Placentia Metrolink Station Design: Project Management includes parking lots, structures, roadway/traffic improvements, and coordination with Metrolink, BNSF, OCTA and the City of Placentia.
Click here to learn more...

transportation services

north coast railroad authority

Project Elements:
  • Construction Management
  • Extensive Local Agency Coordination

Program Management and Bridge Rehabilitation Project Management: As the Program Manager, AndersonPenna is responsible for oversight of the planning, design, environmental, and construction management of a $68.8 million 62-mile linear project that includes track, a $6.0 million bridge repair contract, and traffic and railroad signals. Click here to learn more...

transportation services

lake state railway company and saginaw bay southern railway

Project Elements:
  • Preparation of a Bridge Safety Program
  • Bridge Inspection of 60 Bridges

Bridge Inspection, Rating, and Safety Management: AndersonPenna provides on-call bridge management services to LSRC and SBS and is assisting with the development of their overall Bridge Management Plan. Click here to learn more...

transportation services

progressive rail incorporated

Project Elements:
  • Capital Improvement and Repair Programming Recommendations
  • Bridge Inspection of 46 Bridges (Missouri) and 32 Bridges (Minnesota/Wisconsin)

Bridge Inspection, Rating and Safety Management : AndersonPenna provides annual bridge inspection and rating services, prepares repair and replacement plan recommendations. Click here to learn more...

transportation services

northwestern pacific company

Project Elements:
  • Capital Improvement and Repair Programming Recommendations
  • Bridge Inspection

Bridge Inspection, Bridge Rating, Load Testing: APP performed inspections, ratings, and load testing, and developed practical repair plans, then field inspected the repairs. Click here to learn more...